  • Location: Hallett, South Australia, Australia
  • Output/fuel: 200MW gas and oil fired
  • Owners: AGL Power Generation, Australia
  • Overview: AGL Hallett Power Station is a peak power station which provides South Australia with electricity in times of high electricity demand. The plant ensures a stable supply of electricity to the state.

Project

AGL Hallett Power Station: Plant view
Unified Operator Interface Solution Enables Remote Operation / AGL Hallet Power Station, Australia

  • Operation date: 2002
  • Project type: Greenfield site
  • Plant configuration:
  • Gas turbines: 12 second hand Frame 5 gas turbines, manufactured under license to GE by John Brown, AEG and Nuovo Pignone, originally located at sites in Australia, Canary Islands, Chile and Finland.
  • Overview: This peak power plant was built in 2001 by AGL in response to growing summer demand in South Australia. It reduces the likelihood that power blackouts will occur and keeps electricity prices stable during periods of peak demand.Yokogawa Australia provided system engineering, installation support and commissioning services for the project. The company also supplied most of the field instruments.

(Customer requirements)

  • Remote control and operation:
    The plant owner needed to remotely operate up to 12 gas turbines from an existing control center in the city of Melbourne which is more than 900 km away from the plant site.
  • Fast track project:
    The project needed to be completed before the arrival of the Australian summer (2002). System equipment had to be delivered within three months of the initial order.
  • Flexible operation:
    The customer called for effective turbine operation to meet the needs for a power station operating in intermittent peaking mode.

(Yokogawa's solution)

  • Unified Operator Interface (UOI):
    The CENTUM CS 3000 / UOI was selected for this project. The control platform in the UOI is the GE Fanuc CIMPLICITY Human Machine Interface (HMI) system, which fully integrates the controls for the turbine and BOP auxiliaries and uses the same screens/formats at both the turbine and BOP HMI displays. The CIMPLICITY HMI used in the UOI is a SCADA based design that fully supports the customer's requirement for remote operation capability.
  • No delivery delay:
    In close cooperation with Yokogawa's factory in Singapore, Yokogawa Australia supplied fully engineered control systems on schedule.
  • Automatic turbine optimizer:
    The embedded automatic optimizer schedules and selects turbines to run to fulfill changing peaking market demands.
  • System

CENTUM CS 3000 / UOI

- Control scope:
Interface to GE SPEEDTRONIC Mark V Turbine Controllers
Balance of Plant (BOP) Control
Interface to ALSTOM SCADA
Interface to electricity market network for load dispatch(Electranet / NEMMCO)

- System equipment:
CENTUM CS 3000 / UOI

업종

  • 전력

    1970년대 중반, Yokogawa는 EBS 전기 제어 시스템 (EBS Electric Control System)의 출시와 함께 전력 사업에 진출했습니다. 그 이후로 Yokogawa는 전 세계 고객에게 최상의 서비스와 솔루션을 제공하기 위한 기술과 역량의 개발을 꾸준히 지속해 왔습니다.

    Yokogawa는 역동적인 글로벌 전력 시장에서 더욱 적극적인 역할을 수행하기 위해 글로벌 전력 솔루션 네트워크를 운영했습니다. 이로 인해 Yokogawa 내에서 보다 긴밀한 팀워크가 가능해져서 글로벌 리소스와 업계 노하우를 하나로 모았습니다. Yokogawa의 전력 산업 전문가들은 각 고객에게 정교한 요구 사항에 가장 적합한 솔루션을 제공하기 위해 협력합니다.

    See More
  • 화력발전

    석탄, 석유 또는 가스를 연료로 사용하는 화력발전은 전 세계적으로 대부분의 전력을 생산하고 있습니다.

    See More

Related Products & Solutions


Top