Safe and Efficient Power Plant Operation / Tuas 1 Power Plant

下载 (62 KB)

Total Solutions Enhance a Plant's Workforce

Map

Location: Tuas, Singapore
Output/fuel: 1200 MW (2 × 600 MW), oil/gas fired
Owners: Tuas Power Pte Ltd, Singapore
Overview: The construction of Tuas Power Station started in the mid 1990s. The plant has steadily grown to be a significant player in the competitive Singaporean electricity market. Stage One of Tuas Power Station is equipped with the country's largest steam generators which are capable of producing 600 MW each.

Project

Tuas Power Station: Plant view
Safe and Efficient Power Plant Operation /
Tuas 1 Power Plant

Operation date: 1999
Project type: Greenfield site
Plant configuration:
Boilers: Babcock-Hitachi, Japan
Steam turbines: Hitachi, Japan
Overview: Yokogawa supplied an integrated distributed control system (DCS) for this plant's very large power generation units as part of the work in stage one. Yokogawa Electric Asia Pte. Ltd., Singapore produced the control system in Singapore and carried out all engineering work.

(Solutions/benefits)
Single source solution:
The plant successfully entered commercial operation on schedule and the plant owner attributed this in part to Yokogawa's good performance in delivering both products and services.
On-time commercial operation:
In addition to supplying Instrumentation & Control (I&C) equipment, Yokogawa handled system design/engineering, configuration, project management, commissioning services and maintenance. Operator/engineer training on a replica simulator and control room design were also provided.

System

Tuas Power Station: Full replica simulator
Full Replica Simulator

Control scope:
Coordinated boiler and turbine controls including:
burner management system
electrical distribution system
water and waste water treatment
other auxiliary plant controls

System equipment:
CENTUM CS
Computer station for unit performance calculation
Full scope, high fidelity training simulator
Sequence event monitoring system
Emergency shutdown system

(Replica Simulator Showcase)
A full scope, high fidelity training simulator was supplied by a wholly owned Yokogawa subsidiary, TechComm Simulation Pty Ltd. This simulator provides training in all aspects of operating complex plant systems. It has made a significant contribution in raising the skill levels of the highly motivated Tuas Power Station workforce.

Central Control Room (CCR) Design by Yokogawa

Tuas Power Station: Control Room Design

(CCR Design Showcase)
Yokogawa also designed the Tuas Power Station's Central Control Room, which has won praise from users for its good operating environment. Our CCR design methodology emphasizes the importance of sound ergonomic design in reducing operator errors and facilitating the smooth running and control of processes.

行业

  • 火电

    使用煤、石油或天然气作为燃料的火力发电占发电量的大部分。

    更多
  • 电力

    在20世纪70年代中期,横河电机发布EBS电子控制系统,从而正式进入电力行业。从那时起,横河电机一直坚持不断发展技术和能力,旨在为客户提供更好的服务和解决方案。

    横河电机凭借着电力解决方案网络,在充满活力的电力市场中发挥着积极的作用。通过结合资源和行业知识,使得团队合作更加紧密。横河电机的电力专业人员们将携手合作,为客户提供适合其复杂要求的解决方案。

    更多

相关产品&解决方案

  • 集散控制系统(DCS)

    横河电机的集散控制系统(DCS) 可实现工业过程的自动化和控制,并提高业务绩效。30,000多套系统的经营者选择采用横河电机的DCS来实现其生产目标。

    更多

置顶
WeChat QR Code
横河电机(中国)有限公司