Yokogawa Corporation of America Receives Analyzer Systems and Shelters Order from Freeport LNG

Yokogawa Corporation of America announces that it has received orders from Freeport LNG for its Liquefaction Facility (LQF) and Pre-Treatment Facility (PTF). The total order value is $15M, which currently includes only the first two trains.

Freeport LNG is constructing liquefaction infrastructure at the existing terminal to provide nominal export capacity of approximately 13.9 million metric tonnes per annum (mtpa) of LNG, which equates to processing approximately 2.0 Bcf/d of pipeline-quality natural gas (feed gas). The feed gas will be derived from the interconnecting instrastate pipeline systems through Freeport LNG's existing Stratton Ridge meter station.

The gas will be pretreated near Freeport LNG's existing metering, compression and underground storage facilities. The pretreated natural gas will then be delivered to the terminal through Freeport LNG's existing gas pipeline. At the terminal, it will be liquefied and then stored in full-containment LNG storage tanks. LNG carriers arriving via marine transit through the Freeport Harbor Channel will export LNG from the terminal.

The added liquefaction capability will not preclude the terminal from operating in vaporization and send-out mode as business conditions dictate. Also, having dual liquefaction and regasification capabilities will not result in any increase in the number of ship transits since the total amount of LNG handled, either by liquefying natural gas or by vaporizing LNG, will not exceed authorized thresholds.

The Liquefaction Process

Each of the three liquefaction trains will utilize a proprietary propane pre-cooled mixed refrigerant process, developed by Air Products and Chemicals, Inc. (Air Products), to produce a nominal 4.64 mtpa of LNG. To prepare the feed gas for liquefaction, it will be pretreated near Stratton Ridge to remove CO2 sulfur compounds, water and mercury, after which compressors will be used to increase the pressure of the natural gas for delivery to the terminal through Freeport LNG's existing 42-inch diameter pipeline.

To convert the pretreated feed gas into LNG, the gas is first cooled with propane refrigerant, after which it is stripped of natural gas liquids (NGLs) via cryogenic distillation in the scrub column. The NGLs are, in turn, stripped of light gases (mostly methane) that are recycle through the main cryogenic heat exchanger (MCHE). Following NGL removal, the primary feed gas from the scrub column is also sent to the MCHE, where it is further cooled inside tube bundles, each made up of several tube circuits, by a lower-temperature mixed refrigerant that flows outside the tubes.

As the feed gas flows up the tubes, it starts condensing by transferring heat to the liquid/vapor mixed refrigerant, which warms up and vaporizes as it flows down the outside of the tubes. The heated mixed refrigerant is then cooled by ambient air, compressed and subsequently chilled by propane refrigerant in heat exchangers, where a portion of the refrigerant condenses. After separating the vapor and liquid streams of mixed refrigerant, both streams are depressurized and admitted to the MCHE to provide cooling for the conversion of methane-rich gas into LNG. The liquid mixed refrigerant stream is depressurized through a liquid expander to increase the overall process efficiency. The high-pressure LNG exiting the MCHE is depressurized through a liquid expander and delivered to the LNG storage tank at near-ambient pressure. Once in the storage tank, the LNG can be pumped through the plant piping to the dock to be loaded onto ships for export.

Project Status and Schedule

Freeport LNG started construction of the liquefaction project in November 2014 and expects to achieve commercial operation of the first liquefaction train in 2018.

Freeport LNG had engaged a joint venture of CB&I and Zachry Industrial to develop a fixed-price turnkey contract price and detailed scope for the project's EPC agreements. The final EPC contract with the joint venture to construct the first two trains of the liquefaction project was signed in December 2013. For the third-train EPC contract, joint venture partners CB&I and Zachry were joined by Chiyoda International Corporation, and the contract was awarded in March 2015.

Freeport LNG selected Air Products and Chemicals, Inc. (APCI) as the liquefaction technology provider for its experience and overall performance of its proprietary cryogenic liquefaction process (C3MR). Over the last four decades, APCI has designed and manufactured over 100 main cryogenic heat exchangers for LNG projects around the globe.

Following financial closing on trains 1 and 2 in November 2014 and on train 3 in April 2015, all three units are now under construction by a joint venture among CB&I, Inc., Zachry Industrial, Inc. and Chiyoda International Corporation.

The first two trains are on schedule to commence operations by September 2018 and February 2019, respectively. The third train is expected to be in operation approximately six months following the second train, or in August 2019.

Key Milestone Activities

Status / Date

Liquefaction Tolling Agreements (Train 1) with Osaka Gas and Chubu Electric

July 2012

Liquefaction Tolling Agreement (Train 2) with BP Energy Company

February 2013

Liquefaction Tolling Agreements (Train 3) with Toshiba Corporation and SK EKS

September 2013

DOE's Authorization to Export Entire Contracted LNG Volume of Initial Three Trains

November 2013

Trains 1 and 2 EPC Contracts Finalized

December 2013

FERC's Issuance of Authorization to Construct and Operate

July 2014

Final Approvals from DOE and FERC

November 2014

Trains 1 and 2 FID/Financial Close

November 2014

Commencement of Construction

November 2014

Train 3 EPC Contract Executed

March 2015

Train 3 Financial Close

April 2015

Liquefaction Train 1 In-Service Date

September 2018

Liquefaction Train 2 In-Service Date

February 2019

Liquefaction Train 3 In-Service Date

August 2019

About Yokogawa
Yokogawa's global network of 92 companies spans over a total of 59 countries. Founded in 1915, the US$3.7 billion company engages in cutting-edge research and innovation. Yokogawa is active in the industrial automation and control (IA), test and measurement, aviation, and other business segments. The IA segment plays a vital role in a wide range of industries including oil, chemicals, natural gas, power, iron and steel, pulp and paper, pharmaceuticals, and food. For more information about Yokogawa, please visit our website www.yokogawa.com.


Top