Escravos Gas Plant Control System Online Migration (Hot Cut Over)

Chevron Nigeria Limited logo
다운로드 (544 KB)

About Chevron Nigeria Limited

Chevron Nigeria Limited
Chevron Nigeria Limited

Chevron Nigeria Limited (CNL) is Chevron's principal subsidiary in Nigeria, one of Africa's most prolific oil-producing countries. CNL and its related companies have done business in Nigeria for more than 90 years and CNL's workforce totals more than 2,000 employees, of which 90 percent is Nigerian. CNL operates and holds a 40 percent interest in 13 concessions covering 2.2 million acres (8,900 km2), predominantly in the onshore and near-offshore regions of the Niger Delta. In 2007, total daily production averaged more than 350,000 barrels of crude oil, 14 million cubic feet of natural gas, and 4,000 barrels of liquefied petroleum gas. The company's net oil-equivalent production in 2007 was 129,000 barrels per day.

Background of This Project

The Escravos Gas Plant is located in the vicinity of the Escravos River, adjacent to the Chevron Nigeria Oil Terminal, on the Bight of Benin. The site is approximately 100 miles southeast of Lagos and 37 miles west of Warri.

The existing Escravos gas plants (hereinafter EGP1&2) process 285 million standard cubic feet of natural gas per day (scfd). This will be increased to 680 million scfd with the completion of a new gas plant (hereinafter EGP3) by 2009.

Yokogawa Electric Korea received an order from Hyundai Heavy Industries (HHI), the project EPC contractor, to replace EGP1&2's existing Honeywell TDC3000 system with the CENTUM CS 3000 system and to install an integrated control system (DCS, SIS, CMS, and FGDS) at EGP3.

The main objective in the EGP1&2 phase of this project was to do an online hot cut over from the legacy Honeywell TDC3000 to the Yokogawa CENTUM CS 3000. The hot cut over involved the Train-1 operating plant and the processes at EGP1&2. This included migration of the existing fire and gas monitoring signals and migration of the existing serial communication interfaces for the existing PLC controlled ESD system and the master surge CCC compressor control system. The contracted work was scheduled to be completed in 90 days.

Summary of Online Hot Cut Over Migration Project

  1. The key business driver for this online system migration: estimated savings of US$2.3 million by not shutting down gas plant operations for 90 days.
  2. Secondary business consideration: by doing the system migration in the second quarter of 2008, operators would have time to familiarize themselves with the new CENTUM CS 3000 control system before the main EGP3 control system is introduced in 2009.
  3. Migration scope: migration of all EGP1&2 control system signals/functions from the legacy Honeywell TDC3000 DCS to the new Yokogawa CENTUM CS 3000 and the migration of 279 digital input signals, 127 digital output signals, 322 analog input signals, 59 analog output signals, 480 WORKPACKs, and 787 loops. WORKPACK means that whole procedure and concerned data in order to HCO work of each loop.
  4. Replacement of existing Honeywell field termination assemblies (FTAs) in marshalling cabinets with new Yokogawa terminal boards.
  5. Project execution period: from the middle of July to the middle of October 2008 (90 days, no days off)

The Challenges and the Results

The greatest challenge in this project lay in carrying out the migration from the existing Honeywell TDC3000 to the new Yokogawa CENTUM CS 3000 without disrupting gas production. This online hot cut over required both systems to be manned by operators during the migration process.

Although this presented a high risk for disruption to ongoing gas processing operations, the work was successfully completed 48 days ahead of schedule and without disruption to operations thanks to detailed planning, risk/mitigation analysis, and a robust execution strategy with a coordinated team approach between CNL/HHI and Yokogawa Korea.

Through the successful execution of this project in just 42 days, CNL was able to avoid a costly shutdown of operations and generated additional savings in labor costs. And by working together on this project, CNL, HHI, and Yokogawa Korea were able to build a strong relationship. Thanks to their efforts, the CENTUM CS 3000 is running smoothly at EGP1&2.

The key success factors were as follows:

  • Mutual trust and effective cooperation by all stakeholders (CNL/HHI/Yokogawa Korea) for the smooth execution and accelerated completion of the project
  • An effective team approach that resulted in the project being driven to a successful conclusion in a highly expeditious manner
  • The preparation of enormous WORKPACKs containing key reference data documents, which eased the cross-checking of process system functionality across both systems before the signal migration was commenced
  • Meticulous planning that ensured a safe and disruption-free changeover
  • Yokogawa Korea's technical leadership and expertise in performing online hot cut overs

Customer Satisfaction

Recognition & Achievement Certificate from CNL

The following quotes are from the DCS-HCO-Lessons Learned Meeting of September 26, 2008:

"The new CENTUM CS 3000 DCS equipment has exhibited excellent performance thus far."

"The DCS vendor provided effective technical leadership throughout the hot cut over and demonstrated a good command of English, avoiding potential communication problems. Technical challenges were encountered throughout the execution phase but these were resolved in an expeditious manner."

"The DCS vendor's sub-contractor panel technicians kept to a demanding work schedule for an extended time period. They contributed significantly to the success of this project. Their work has been critically important and it required extensive concentration and dedication from them while working in cramped conditions. Not a single isolation or installation mistake occurred! — Congratulations."

Excellent Performance Certificate from HHI

Receipt of Recognition & Achievement Certificate from CNL

"The EGP3 project leadership team recognizes your efforts for being part of the team that successfully executed the DCS — Hot Cut Over without LTI and unnecessary / prolong shut down of the Gas Plant. Thank you for a job well done on behalf of Engineering, Construction & Operation Teams."

Receipt of Excellent Performance Certificate from HHI

"This is to certify that Yokogawa Korea has supplied the CENTUM CS 3000 FIO R3 system to EGP-3 onshore project in Chevron Nigeria Limited (CNL) via Hyundai Heavy Industries (HHI) and HOT CUT-OVER (HCO) work between the existing HONEYWELL TDC3000 system and new YOKOGAWA CENTUM CS 3000 system has been successfully completed in accordance with HCO procedure."

<System Details>

For hot cut over

DCS: CENTUM CS 3000 R3 with Vnet/IP
Total I/O: 787

For EGP3

DCS: CENTUM CS 3000 R3 with Vnet/IP
SIS: ProSafe-RS Safety Instrumented System
FGDS: Autrosafe fire and gas detection system
CMS: 3500 condition and monitoring system
Total I/O: 4,610

업종

  • 업스트림

    업스트림(Upstream) 산업에는 유전 또는 해저의 원유 및 천연가스의 채취 및 생산을 위한 유정제어, 증류, 분리 및 제품 완성을 포함한 해상 및 육상 플랜트가 포함됩니다.

    석유는 육상으로 옮겨져야 하는 관계로 운송 전에 분리 작업이 필요합니다. 1차 및 2차 분리 단계는 일반적으로 가스 흐름, 물 흐름 및 오일 흐름의 3단계로 분류됩니다. 가스 이동은 파이프라인을 필요로 하며, 이동하기 전에 상류 공정에서 분류 공정을 거치게 됩니다. 액체는 탱크 또는 파이프라인에 넣고 운송을 하므로 정확한 레벨 측정이 가능한 레벨계가 필요합니다.

    See More
  • 오일 및 가스

    Yokogawa는 해상 및 육상 시설에서 파이프라인, 터미널 및 심해 운전에 이르기까지 석유 및 가스 사업의 모든 부분에서 풍부한 경험을 보유하고 있습니다. 우리는 안전을 강화하고 정확하고 신뢰성 있는 운전을 보장하며 플랜트 효율을 높이는 솔루션을 제공합니다.

    See More

Related Products & Solutions

  • DCS Migration / Replacement

    변화하는 프로세스의 요구 사항을 충족할 수 있도록 설계된 DCS 마이그레이션 서비스를 통해 '미래 지향적인' 시스템으로 전환하세요.

    See More
  • SIS (Up to SIL 3) ProSafe-RS

    ProSafe-RS는 IEC 61508에 명시된 SIL(Safety Integrity Level) 3을 충족하는 것으로 독일 인증 기관(TÜV)의 인증을 받은 안전 계측 시스템입니다.

    See More
  • 컷오버 계획 및 실행

    신중한 계획과 실행을 통해 요꼬가와는 고객의 시스템을 안전과 합리적인 비용, 가치를 더한 마이그레이션 프로세스를 실현 할 수 있도록 도와줍니다.

     

    See More